HOV Lanes, Mussel Shoals to Casitas Pass Road |
Description: Near the community of Mussel Shoals in Ventura County to just south of Casitas Pass Road in Santa Barbara County. Construct HOV Lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura, Santa Barbara |
City | Carpinteria |
Zip Code | 93001, 93013 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 23 |
Caltrans District |
07 |
County/State Route | Santa Barbara 101 |
Postmile Begin/End | 0 2.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1603 | 1602.79 |
Lane Miles Added (HOV) | 12 | 12 |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 108528 | 108,495 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Ravi Ghate | (213) 897-5593 | ravi.ghate@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Ravi Ghate | (213) 897-5593 | ravi.ghate@dot.ca.gov | |
Right of Way Phase |
Caltrans | Ravi Ghate | (213) 897-5593 | ravi.ghate@dot.ca.gov | |
Construction Phase |
Caltrans | Ravi Ghate | (213) 897-5593 | ravi.ghate@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Elhami Nasr | (213) 897-0227 | elhami_nasr@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
IIP Augmentation |
$0 | $4,170 | $4,170 | ||||
CMIA |
$131,600 | $-50,307 | $81,293 | ||||
Non-bond Funding | |||||||
State/Federal* |
$19,870 | $-4,170 | $15,700 | ||||
Total**** | $151,470 | $-50,307 | $101,163 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$4,400 | $670 | $5,070 | $5,118 | |||
Design(PS&E) |
$14,800 | $-2,621 | $12,179 | $10,806 | |||
Right of Way |
$670 | $1,951 | $2,621 | $2,441 | |||
Construction |
$131,600 | $-50,307 | $81,293 | $74,195 | |||
Total* | $151,470 | $-50,307 | $101,163 | $92,561 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 11/18/2008 |
|
07/02/2007 11/18/2008 |
100 | 07/02/2007 12/18/2008 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/01/2008 10/14/2010 |
|
11/01/2008 10/14/2010 |
100 | 12/19/2008 06/30/2011 |
-2 -9 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/01/2009 10/14/2010 |
|
01/01/2009 10/14/2010 |
100 | 03/25/2009 06/22/2011 |
-3 -8 |
|
Begin Construction Phase
End Construction Phase |
05/12/2011 08/25/2014 |
|
05/12/2011 08/25/2014 |
98 | 01/03/2012 06/27/2017 |
-8 -35 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2015 01/01/2017 |
|
09/01/2015 01/01/2017 |
0 | 07/20/2018 09/30/2019 |
-35 -33 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 09/03/2010 | 09/03/2010 | 0 | 09/03/2010 | 0 | ||
Implementation Date | 10/01/2010 | 11/18/2010 | 0 | 12/01/2010 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1603 | 1602.79 |
Lane Miles Added (HOV) | 12 | 12 |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 108528 | 108,495 |
Bond Funding Cost | |
---|---|
Adopted: |
$131,600,000 |
Current Approved: |
$5,070,000 |
Actual Expenditures: |
$5,118,000 |
Status as of December 31, 2023.