HOV Lanes, Mussel Shoals to Casitas Pass Road

Description: Near the community of Mussel Shoals in Ventura County to just south of Casitas Pass Road in Santa Barbara County. Construct HOV Lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura, Santa Barbara
City Carpinteria
Zip Code 93001, 93013
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
07
 
 
County/State Route Santa Barbara 101
Postmile Begin/End 0 2.2
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1603    1602.79  
Lane Miles Added (HOV)  12    12  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)  108528    108,495  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Ravi Ghate (213) 897-5593   ravi.ghate@dot.ca.gov
Design (PS&E) Phase
Caltrans Ravi Ghate (213) 897-5593   ravi.ghate@dot.ca.gov
Right of Way Phase
Caltrans Ravi Ghate (213) 897-5593   ravi.ghate@dot.ca.gov
Construction Phase
Caltrans Ravi Ghate (213) 897-5593   ravi.ghate@dot.ca.gov
 
Corridor System Management Plan
Caltrans Elhami Nasr (213) 897-0227   elhami_nasr@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
IIP Augmentation
$0 $4,170 $4,170
CMIA
$131,600 $-50,307 $81,293
Non-bond Funding
State/Federal*
$19,870 $-4,170 $15,700
 
Total**** $151,470 $-50,307 $101,163

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$4,400 $670 $5,070 $5,118
Design(PS&E)
$14,800 $-2,621 $12,179 $10,806
Right of Way
$670 $1,951 $2,621 $2,441
Construction
$131,600 $-50,307 $81,293 $74,195
 
Total* $151,470 $-50,307 $101,163 $92,561

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

11/18/2008 
 

 
07/02/2007 

11/18/2008 
100  07/02/2007 

12/18/2008 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2008 

10/14/2010 
 

 
11/01/2008 

10/14/2010 
100  12/19/2008 

06/30/2011 
-2 

-9 
Begin Right of Way Phase

End Right of Way Phase
01/01/2009 

10/14/2010 
 

 
01/01/2009 

10/14/2010 
100  03/25/2009 

06/22/2011 
-3 

-8 
Begin Construction Phase

End Construction Phase
05/12/2011 

08/25/2014 
 

 
05/12/2011 

08/25/2014 
98  01/03/2012 

06/27/2017 
-8 

-35 
Begin Closeout Phase

End Closeout Phase
09/01/2015 

01/01/2017 
 

 
09/01/2015 

01/01/2017 
07/20/2018 

09/30/2019 
-35 

-33 
Corridor System Management Plan
Adoption Date 09/03/2010    09/03/2010  09/03/2010 
Implementation Date 10/01/2010    11/18/2010  12/01/2010 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1603 1602.79
Lane Miles Added (HOV) 12 12
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 108528 108,495

Bond Funding Cost
Adopted:
$131,600,000
Current Approved:
$5,070,000
Actual Expenditures:
$5,118,000

 

Status as of December 31, 2023.